Stage 4 – Phase B

  • Construction to continue along the west side of U.S. 1 for construction of SB lanes.
  • Construction to continue for U.S. 1 SB on ramp from the PA Turnpike Toll Plaza.
  • Temporary paving to be placed in the median of U.S. 1 under Bristol Road overpass to accommodate traffic shifts in future stages.