What bridges will be replaced using a detour and what bridges will be replaced using a staged construction sequence?

Based on initial indications, the US 1 mainline bridge over Highland Avenue and the bridge carrying PA 413 Pine Street over US 1 will be staged construction.

The West Interchange Road bridge and the Corncrib Lane bridge will most likely be detours. With the lower volumes of traffic, the contractor can demolish them and then get them rebuilt a lot quicker than a staged construction. This is still under analysis.