Stage 5

  • Construction of the Bristol Rd. bridge replacement and approach roadway to be performed.
  • Full depth reconstruction to be performed on North River Dr. and Belmont Ave.

Stage 4 – Phase D

  • Full depth reconstruction to be performed along the EB side of Street Road for construction of EB lanes.
  • Median pier construction to begin for Bristol Rd. over U.S. 1.

Stage 4 – Phase C

  • Full depth reconstruction and widening to be performed along the north side of Street Road for construction of WB lanes.
  • Construction to continue for U.S. 1 NB off ramp to the PA Turnpike Toll Plaza.
  • Temporary paving to be placed along the outside shoulders of U.S. 1 under Bristol Road overpass to accommodate traffic shifts in future stages.

Stage 4 – Phase B

  • Construction to continue along the west side of U.S. 1 for construction of SB lanes.
  • Construction to continue for U.S. 1 SB on ramp from the PA Turnpike Toll Plaza.
  • Temporary paving to be placed in the median of U.S. 1 under Bristol Road overpass to accommodate traffic shifts in future stages.

Stage 4 – Phase A

  • Full depth reconstruction and widening to begin along the west side of U.S. 1 for construction of SB lanes.
  • Construction of U.S. 1 SB on/off ramps to take place for connecting to Street Road and the PA Turnpike Toll Plaza.
  • Full depth reconstruction to be performed for Red Roof Inn access road.

Stage 3

  • Full depth reconstruction of U.S. 1 median and inside lanes to be performed.
  • Construction of U.S. 1 SB on-ramp from Street Road to be performed.
  • PA Turnpike Slip Ramp from Horizon Blvd. to be realigned and reconstructed.

Stage 2 – Phase C

  • Construction to continue along the east side of U.S. 1 for construction of NB lanes.
  • Full depth reconstruction to be performed along the median of Street Road for construction of EB and WB lanes.

Stage 2 – Phase B

  • Construction to continue along the east side of U.S. 1 for construction of NB lanes.
  • Full depth reconstruction and widening to be performed along the north side of Street Road for construction of WB lanes.
  • Widening to be performed along west side of PA Turnpike Slip Ramp to/from Street Road for adding a turn lane.

Stage 2 – Phase A

  • Full depth reconstruction and widening to begin along the east side of U.S. 1 for construction of NB lanes.
  • Construction of U.S. 1 NB on/off ramps to take place for connecting to Street Road and the PA Turnpike Toll Plaza.
  • Full depth reconstruction and widening to be performed along the south side of Street Road for construction of EB lanes.
  • Median pier construction to begin for U.S. 1 over Street Road and U.S. 1 over the PA Turnpike.
  • A portion of Neshaminy Blvd. to be realigned and reconstructed in the area of the PA Turnpike Interchange.

Stage 1 – Phase B

  • Temporary paving to be placed in the median of U.S. 1, Street Road and the PA Turnpike Interchange ramps to accommodate traffic shifts in future stages.
  • Construction to continue of the off-alignment local roads (Red Roof Inn driveway and T-329 relocations).